New Study Cubicles on the 4th Floor
The new study cubicles will be delivered to the
library on February 14 or shortly after.
Installation has not been scheduled but shouldn’t be too far
behind. I will let you know as soon as I
get a date. Carpenters started
disassembling some study carrels yesterday in order to make room on the 3rd
floor for twelve of the new cubicles.
Some of the carrels will be moved up to the 4th floor.
EPIC Training Project
The University Administration has asked us to
re-examine all options to accommodate the need to train 6,500 people in 9,000
training sessions between April and October.
I will be meeting with a group of people on the 14th to discuss various
options. In the meantime Facilities
Management is helping us to figure costs and strategies in order to find the
best outcome for the library.