The EPIC “command center” is scheduled to cease
operations on the 4th floor on Friday, November 29. After that all EPIC help desk questions will
go to UAHN staff in their regular offices.
The schedule calls for computers to be removed during the week of December
2nd and for the walls to come down the following week. We have asked for 20 of the tables to be
gifted to us to be used for student study.
The College of Medicine accreditation team will be
here in mid-January. Our goal is to have
the 4th floor useful for study and looking nice before the visit! There are 24 of the new study cubes currently
at the UA warehouse. We are hoping to
have these installed on the 4th floor beginning in the third week of
December. We also hope to purchase 24
additional cubes (using the rent money from EPIC) that will be installed at the
same time. The remainder of the floor
will be filled with study tables, also to be purchased with EPIC rent money.