Progress on the recording studio has been hard to
see but will become evident in January.
Facilities Management will be working in the first AV listening room to
remove the counter and to paint the room.
That work is scheduled to finish by January 17th. Soon after that (we hope), equipment and
soundproofing will be installed and we will have an operational recording
studio. BioCommunications will provide
training to our desk staff and to the ITS staff at the Help Desk. Training will be very basic as users of the
room will be expected to know how to run the equipment or to bring someone who
does. The studio will be on the campus
room scheduling system and available to AHSC faculty and students.
Wednesday, November 27, 2013
Friday, November 15, 2013
Staff Lounge
We have invited the STAFF of the VETS Center to
feel free to use our staff lounge, as we have with other groups sharing space
in the building. It seems that most of
the VETS Center staff are undergraduate veterans.
Friday, November 8, 2013
VETS!
The VETS Center will have a “soft” opening next
week. It will be staffed and open to
veterans. However the grand opening with
dignitaries, etc. won’t happen until January.
VETS staff members are working on ordering furniture so we will be
loaning them some tables and chairs until theirs arrive.
Friday, October 25, 2013
NYT, Carol and the LAC
-->
Congratulations Carol
An article in the New York Times refers to work
that Carol did. She is the anonymous
“medical librarian” mentioned in the article.
The story also links to an article in The Journal of the American
Geriatrics Society for which Carol is a co-author.
http://newoldage.blogs.nytimes.com/2013/10/24/hiring-an-end-of-life-enforcer/?_r=0
http://newoldage.blogs.nytimes.com/2013/10/24/hiring-an-end-of-life-enforcer/?_r=0
Library Advisory Committee
Our Library Advisory Committee will hold its first
meeting of the year on Monday. We have
faculty and student representatives from each of the AHSC colleges on the
committee. They serve as a vehicle for
communication with the colleges and offer feedback from the students and
faculty members that we serve. Our new
student representative from the College of Pharmacy has already distributed a
survey to classmates asking about the library.
We’ll hear the results on Monday.
Friday, October 11, 2013
Lights! Camera! Action! Chairs! Tables!
Recording Studio
We are partnering with BioCommunications on
planning and constructing the new mini-recording studio (any ideas for what we
should call this room?) which will be created in the first AV listening room as
you enter Java City. BioComm has worked
up the specifications for equipment and will handle ordering it. Facilities Management will be taking out the
counter and repainting the inside of the room to provide good color balance for
videos. Professional lighting will be
installed as well as a high definition camera and computer controls. We already have people who want to sign up to
use the room. Once the equipment is
ready for use BioComm will offer some training for our staff so that we can
answer basic questions. Anything beyond
basic questions will be handled by BioComm.
After EPIC
We are getting price quotes for new study cubes
for the 4th floor and new study tables for the 3rd and 4th floors. With those in hand we will be ordering chairs
for the new tables and to replace many of our older, deteriorating chairs. I think we will be asking for volunteers in
the future to form teams to deploy our new chairs and to redistribute some of
the other chairs that have wandered around the building.
Thursday, October 3, 2013
More EPIC
The EPIC “command center” is scheduled to cease
operations on the 4th floor on Friday, November 29. After that all EPIC help desk questions will
go to UAHN staff in their regular offices.
The schedule calls for computers to be removed during the week of December
2nd and for the walls to come down the following week. We have asked for 20 of the tables to be
gifted to us to be used for student study.
The College of Medicine accreditation team will be
here in mid-January. Our goal is to have
the 4th floor useful for study and looking nice before the visit! There are 24 of the new study cubes currently
at the UA warehouse. We are hoping to
have these installed on the 4th floor beginning in the third week of
December. We also hope to purchase 24
additional cubes (using the rent money from EPIC) that will be installed at the
same time. The remainder of the floor
will be filled with study tables, also to be purchased with EPIC rent money.
Friday, September 27, 2013
EPIC Update
EPIC training is scheduled to end around October
25th. During the following week phones
will be installed to convert the 4th floor into a “command center” for the EPIC
launch. At 3 AM on November 1st
(Halloween night!) EPIC will “go live”.
The command center will be in operation 24/7 through the month of
November. About 150 employees will be
there at one time or another to provide help desk services to UAHN. Security guards will be stationed at the
front door during hours when the library is closed. We will be meeting with UAHN soon to discuss
plans for their exit from the floor!